AFC - No./So. Fk Asotin Cr. Jct. ISA

AFC is a permanent instream PIT tag interrogation site located at the confluence of the North and South Forks Asotin Creek, a tributary of the Snake River. As of 10/25/2018 all previous components present at AFC have been replaced and upgraded. The site consists of a single 20-foot antenna in the North Fork (antenna ID 1), a single 15-foot antenna in the South Fork (antenna ID 2) and two rows containing a 20 and 15-foot antenna each (antenna IDs 3-6) in the mainstem of Asotin Creek below the confluence. All new antennas are constructed of HDPE and installed in flat-plate configuration. Each antenna is powered by a Biomark IS1001 (ACN) and the ACNs are connected to a Biomark IS1001-MTS master controller. The antennas were built and installed by WDFW. The site is connected to grid power to charge the battery bank powering the detection system. A cellular modem is installed on site to provide remote communication and allow for automated data collection, however, only manual data collection from the IS1001-MTS will occur at AFC until further notice. Prior to the upgrade, the site consisted of six muxed antennas powered by an FS1001M.

Operated by:

SRSRB

First year:

2009

Last year:

2019

RKM:

522.234.025

Site Contacts

Steward

Steve Bennett
bennett.ecological@gmail.com
(435) 757-5668

POC

Ethan Crawford
Ethan.Crawford@dfw.wa.gov
(509) 751-0823

Map

Photo Gallery

Operational Dates

Year Start Date End Date Notes
2014 1/1/2014 1/1/2015
2010 1/1/2010 1/1/2011 Data up to Dec 18 originally submitted as Passive Recapture events. Those events were removed in 2017 and resubmitted as interrogation records.
2015 1/1/2015 1/1/2016
2016 1/1/2016 1/1/2017
2017 1/1/2017 1/1/2018
2011 1/1/2011 1/1/2012 First complete year of operations
2012 1/1/2012 1/1/2013 Site down March 26-28. Mux replaced April 4. Antennas 3,4,6 were removed from the site from August 15-30.
2013 1/1/2013 1/1/2014 No reported interruptions in operation.
2009 7/30/2009 1/1/2010 Data from this year of operations originally submitted as Passive Recapture events. Those events were removed in 2017 and resubmitted as interrogation records.
2018 1/1/2018 1/1/2019
2019

Current and Historic Site Configurations

Config Seq: 110

Start Date: 10/26/2018

End Date:

Config Seq: 100

Start Date: 7/30/2009

End Date: 10/26/2018