Site Type

Site Name

 

ESJ - Easton Acc. Pond

Easton Acclimation Pond Outfall

Operated by:

PSMFC

First year:

1999

Last year:

2017

RKM:

539.325

Site Contacts

Steward

Nicole Tancreto
ntancreto@psmfc.org
(503) 595-3141

POC

Don Warf
dlwarf@psmfc.org
(509) 735-2773 x1

Map

Photo Gallery

Operational Dates

Year Start Date End Date Notes
2014 1/6/2014 5/22/2014 Fish delevered on January 6. Last fish detected on May 22.
2015 1/13/2015 5/12/2015
2016 1/25/2016 5/13/2016
2017
1999 3/14/1999 5/24/1999 Dates and times based on first/last reported detections.
2000 1/28/2000 6/5/2000 First year of operation. Contact YIN for the actual dates of release.
2001 1/22/2001 5/30/2001 Screens pulled on 3/16/01; site dewatered by 5/30/01.
2002 1/28/2002 6/6/2002 Fish delivered 1/15; screens pulled 3/15; no idea when the ponds were emptied.
2003 2/5/2003 3/29/2003 Fish were delivered to the ponds on Feb 5-6. Fish were forced out on March 28.
2004 1/21/2004 5/21/2004 Fish were introduced into the Easton Acc. ponds on 1/21/04, per YN staff. Volitional release began on March 15, 2004. All remaining fish were pushed from the ponds on May 14, but water was left running until May 21 to prevent stranding between the ponds and the river.
2005 1/26/2005 4/28/2005 Fish were introduced into the Easton acc ponds on or before January 26, 2005. Volitional release began on March 9. All remaining fish were pushed out on April 28.
2006 1/18/2006 5/31/2006 Fish were transferred into the Easton Acclimation Ponds on Jan. 18-19, 2006. Fish were allowed to volitionally exit the ponds beginning on March 15. All fish were flushed out on May 15, 2006 and screens were pulled to allow for volitional release. The Easton Acc Pond was dewatered on May 31, 2006.
2007 1/23/2007 6/20/2007 Fish were ponded at Easton on Jan. 23-24, 2007. Volitional release began on March 15, 2007. All remaining fish were forced from the ponds on May 15, 2007. The ponds were completely dewatered on June 20, 2007.
2008 1/8/2008 5/22/2008 Fish were ponded at Easton on January 8. 2008. The volitional release began at 10AM on March 14. Any remaining fish were forced out of the ponds on May 14, into the channels above the PIT tag detectors. All remaining fish in the release channel were pushed throught the PIT tag detectors on May 22, 2008.
2009 1/20/2009 5/18/2009 Fish were ponded on Jan. 20-21. The volitional release began on March 16. All remaining fish were forced from the ponds on May 15.
2010 1/11/2010 6/1/2010 Fish were ponded on January 11-12, 2010. The screens were pulled on March 15 to allow volitional egress. The facility was shut down on June 1.
2011 1/13/2011 5/17/2011 Fish were delivered to the Easton acclimation ponds on January 13. Volitional release began on March 15. Remaining fish were pushed out on May 17.
2012 1/14/2012 5/16/2012 Fish delivered sometime in January. Volitional release began on March 15. Remaining fish were forced out of the pond and channel on May 16.
2013 2/4/2013 5/17/2013 Fish were delivered to pond by January 10. Raceways and creek were cleared of fish May 15-17.

Current and Historic Site Configurations

Config Seq: 110

Start Date: 1/22/2001

End Date:

Config Seq: 100

Start Date: 3/14/1999

End Date: 1/22/2001

Event Logs