Operational Dates

Year Start Date End Date Notes
2014 1/21/2014 5/16/2014 Fish delivered to pond on January 21. Site shutdown May 16.
2015 1/14/2015 5/8/2015
2016 1/25/2016 5/15/2016
2017
2000 2/18/2000 6/3/2000 First year of operation. Contact YIN for the actual dates of release.
2001 3/13/2001 5/30/2001 Screens pulled on 3/15/01; site dewatered by 5/30/01.
2002 2/20/2002 6/6/2002 Fish delivered 2/20; screens pulled 3/15; no idea when the ponds were emptied.
2003 2/11/2003 5/16/2003 Fish were delivered to the ponds on Feb 11-13. The scheduled release is documented as beginning on March 14. Remaining fish were crowded from ponds on May 15. Last tags were detected in the exit channel on May 16.
2004 2/20/2004 6/1/2004 Fish were introduced into the Jack Creek Acc. ponds on Feb. 20, per YN staff. Volitional release began on March 15, 2004. All remaining fish were pushed from the ponds on May 14, but water was left running to prevent stranding between the ponds and the river. The last detection occurred just after midnight on May 23. The channel was dry when the computer platform was decommissioned on June 1.
2005 1/26/2005 4/28/2005 Fish were introduced into the Jack Creek acc ponds on or before January 26, 2005. Volitional release began on March 9. All remaining fish were pushed out on April 28.
2006 2/13/2006 5/10/2006 Fish were first delivered to four of the Jack Creek Acclimation Ponds on February 13, 2006. Additional fish were delivered to two other ponds on March 6. Fish were allowed to volitionally exit the ponds beginning on March 15. Jack Creek fish were forced on April 28, 2006 because of intake plugging from high turbid water. The ponds were dewatered on May 10, 2006.
2007 3/1/2007 6/1/2007 Fish were ponded into Jack Creek Acc. Facility on March 1 & 2, 2007. Volitional release began on March 15, 2007. All remaining fish were forced from the ponds on May 15. Data collection was interrupted for almost three days between May 18-21, and for almost five days between May 24-29. The facility was dewatered, and data collection terminated, on June 1.
2008 3/10/2008 5/15/2008 Fish were first ponded at the Jack Creek facility on March 10, 2008. The screens were removed on April 1, to allow volitional egress. Any remaining fish were forced from the raceways on May 14, into the channels above the PIT tag detectors. The channels were drained on May 15.
2009 2/19/2009 5/18/2009 Fish were ponded on Feb. 19. The volitional release apparently began on Mar. 20. All remaining fish were forced from the ponds on May 15.
2010 2/16/2010 5/22/2010 Fish were delivered to the acclimation ponds on or before Feb. 16, 2010. The screens were pulled on March 15 to allow volitional egress. All remaining fish were pushed out on May 11. The facility generators were powered down on May 22 around 18:00 PDT.
2011 2/17/2011 4/7/2011 Fish were ponded into the Jack Creek Acc. Ponds on Feb. 17-18, 2011. Volitional release began on 15mar11. Due to an extraordinary flood event, most fish were evacuated from the facility on 31mar11. Many of these fish were released directly into the Teanaway River without passing through the exit channels containing the PIT tag detectors. All remaining fish were pushed from the ponds, through the exit channels on 07Apr11.
2012 3/19/2012 5/15/2012 Fish delivered to pond on March 19. Fish were forced out of raceways on May 15.
2013 2/4/2013 5/17/2013 Fish were delivered on February 14. Fish were cleared from site on May 17.

Current and Historic Site Configurations

Config Seq: 110

Start Date: 1/22/2001

End Date:

Config Seq: 100

Start Date: 2/18/2000

End Date: 1/22/2001