1995 Event Log GOJ -- Litte Goose Juvenile ============================================= 11-02-95 polling stopped as of today. --jen 10-11-95 Visited for a maint. check. Reset the slide gate PLC modem. Everything else checks ok. -Warf- 09-29-95 Repaired exciter connections at diversion exit. timer\ tags are now working. -Livingston- 09-28-95 Added DTAM mirco to the slide gate PLC. Also added "Divert During Sample" switches to each slide gate. Removed old electronics. -Warf- Note: The divertion was down from 9/26/95 at 7:00am to 9/29/95 at 7:00am. 09-20-95 Replaced controller 24, Was locking up. tested good. -Livingston- 09-15-95 Visited for maint. check. No problems found. -Warf- 08-29-95 Mort tunnel is back online and has new firmware installed. -Livivngston- 08-07-95 Replaced reader card for coil 4E. tested good. Also the mortality mntr is now back on line. -Livingston Mon Jul 31 14:08:57 PST 1995 A file(s) was missed while polling this site. When someone is here during PSMFC office hours it will be downloaded and processed. --automated message system 07-30-95 Replaced timer pcb in controller 22. Sticks tested at 95% or better. -Livingston- 07-29-95 controller 22 was thought to have been locking up and was was changed out. looking at the raw data file it was found that it was still working but the daily report was showing no fish or timer tags. The Time and Date is wrong and would not accept a time stamp. This will be corrected sun 7/30. the coils 48,4a,(B-seperator) 50,52, (sample rm) are working. Stick test ran better than 95% -Livingston- 07-28-95 Controller for B separator and sample room tunnels was locked up. Reset to bring back on line. Retuned coil 4E. -Warf- 07-26-95 Replaced exciter at B-seperator. ran sticks at better than 95 07-26-95 Site personel report the cooling water for the exciters was turned on about two weeks ago. -Warf- 07-25-95 File was not manually closed by site personel at 7:00am. This resulted in a partial timer tag file. -Warf- 07-20-95 Sample room tunnel at goose was tested with sticks at 100 0.000000e+00fficiency. informed Todd that he was was monitoring the wrong printer. Mort tunnels are still down with no estimated completion date. -Livingston- 07-13-95 The hardware modification was done to the PLC at 0705 to override the sample gate. The slide gates are now diverting at all times -Livingston- 06-30-95 Replace exciter on B-seperator gate to improve efficiency. -Livingston- 06-14-95 Replaced floppy drive in main computer and bad monitor. Maint. check found no problems. -Livingston- 06-12-95 Rex Baxter (Corps Biologist at the Project) reports the following releases from transport raceways to the river on the following dates at Little Goose Dam: May 6, 1995 -- 2 raceways May 10, 1995 -- 3 raceways May 11, 1995 -- 6 raceways -Stein- 06-10-95 The mortality mntr is now operating. unit tested o.k. Rex Baxter has been notified. Raised amperage on the sample room exciter to improve efficiency. Maint check found no problems. -Livingston- 06-05-95 Replaced exciter on A-sep gate (coil 44,46) to improve efficiency. Ran sticks at 100Overall maint. check found no problems. -livingston- 05-30-95 Replaced exciter for the sample room tunnel. (per Livingston) -Warf- 05-26-95 Slide gate electronics have been modified to overcome the the mechcanical drag that is slowing down the gate on the B side. The new modification allows the gate to respond sooner. Efficiency has gone up by 200n the B side. -Warf- 05-25-95 goj95144.a did not load properly. i am trouble-shooting the problem. --jen 05-14-95 Retuned B side separator tunnel. Ran sticks at 100 -Warf- 05-12-95 Retuned all separator coils. Ran sticks with 900r better efficiency. -Warf- 05-08-95 B-side slide gate is sticking. Jim Simonson to look at it tomorrow. -Warf- 05-02-95 Coils A0 and A6 were found to be swapped at the exciter. We do not know for how long. -Warf- (10-26-95) 04-30-95 All exciters have been modified due to weak tags manufactured this year. Both slide gates have been modified to be activated by 4 coils. -Warf- 04-19-95 Site separator/gate tunnels stick tested with 90 or better results by Livingston. -Warf- 04-14-95 Controller 25 down. Replaced with controller from MCJ with bad card slots. This will work because controller 25 has only 4 reader cards. -Warf- 04-12-95 Coils A0 and A6 were found to have return lines swapped at the exciter. Problem was corrected. Retuned coils A0 A2 A4 48 4A 4C 4E A6 A8 and AA. -Livingston- 03-30-95 System watered up for the season. Site is tuned and ready. -Warf- ===============------ EOF GOJ ---===================