EVENT LOG FOR SITE PRA The first line of each entry contains a date/time stamp & who is reporting. The most recent entry is listed first. Date Time Who ---------- ----- -------- 08/19/2013 13:37 bturley@ 08:HighTemp: High temp alarm for XCVR 08 acknowledged. 07/19/2013 07:50 Brett O&M visit on 7/16. Tuned and tested all transceivers. Did computer updates and re-booted computers. 05/03/2013 05:45 Brett O&M visit on 4/23/13. Checked the tune of all ladder transceivers except OLAFT. Installed the FS2001 system at the bypass trailer. Updated computers. OLAFT power is down due to construction at the dam. It will be back in operation by mid June. 04/26/2013 07:45 bturley@ 02:LowExcCurrent,02:TestTagFailure,04:TestTagFailure: Low exciter current alarms occurred while tuning the transceiver. Test tag failures acknowledged. 04/15/2013 08:49 Brett The right ladder transceivers (05, 06,07, 08)were activated on Monday, 4/15/13 at 06:30 PST. 04/10/2013 06:19 Brett Power has been shut off to the data computers as of Monday afternoon 4/11 due to construction at the site. The power probably will not be restored until Thursday 4/14 or Friday 4/15. The right ladder is still down due to construction on the ladder. The left ladder is watered up and interrogating. I will check transceiver buffers to find any detected tags on my site visit when power is restored. 03/21/2013 08:38 Brett I created file PRA13071.ALL to fill in the data gap caused when power was lost on the data computers from 3/12/13 at 09:00 PST to 3/14/13 at 09:26 PST. I downloaded the buffers from the transceivers and found no detections during the time the computers were down. 03/18/2013 09:43 Brett There was a power outage to the data computers on 3/12 at approximately 09:30 PST. The computers were powered back up on 3/14 at 09:26 PST. I downloaded the transceiver buffers of 01, 02, 03 and 04. There were no detections during the time the data computers were down. Transceivers 05, 06, 07 and 08 are still dewatered. The cause of the power outage was probably the construction taking place on the fish ladder adjacent to the data computer room. 02/25/2013 14:43 Brett Site visit on 2/19/13. Updated computer software and renewed firewall and anti-virus license. OLAFT power is shut down during some construction in and around the fish trap. Also fixed malfunctioning test tag on transceiver 04. 02/21/2013 08:33 bturley@ 04:TestTagFailure,07:LowExcCurrent: Test tag failures and low current alarms due to dewatered ladder. 02/19/2013 10:05 bturley@ 06:LowExcCurrent,07:LowExcCurrent,08:LowExcCurrent: Low current alarms caused because the ladder is dewatered. Transceivers were placed in standby to prevent further alarms 02/19/2013 10:04 bturley@ 04:TestTagFailure: Test tag failures acknowledged 01/09/2013 13:58 Brett The left ladder was watered back up on 12/27/12. The right ladder was dewatered on the same day. No word yet as to when the right ladder will be watered up. 01/02/2013 00:00 PTOC_Bot Annual log file initiation for PRA #### End of Event Log for PRA ###