EVENT LOG FOR SITE UWE The first line of each entry contains a date/time stamp & who is reporting. The most recent entry is listed first. Date Time Who ---------- ----- -------- 10/29/2013 12:23 bentrusc UWE site lost power and was down from 9/5/13 at 04:30 until 10/14/13 at 10:45. The thermoelectric generator failed, resulting in a loss of power to the site until a replacement TEG could be installed. A replacement TEG was installed on 10/14/13. Data from 10/14 through 10/22 was uploaded manually, as the power failure also caused the battery supply for the CR1000 to fail. A replacement battery for the CR1000 was installed on 10/22, and data is being automatically uploaded daily. 01/02/2013 00:00 PTOC_Bot Annual log file initiation for UWE #### End of Event Log for UWE ###