EVENT LOG FOR SITE VC2 Most recent activity to be listed first. First line of each entry lists date, time and who is reporting. Subsequent lines of each entry aligned under Time column. Do not use tabs, only spaces. Date Time Who What ---------- ----- -------- ----------------------------------------------- 11/06/2003 15:56 Dave Bill Wassard notified me today that both Valley Creek systems have mechanical problems. The VC1 computer hard drive crashed on October 4. The starter on the VC2 generator failed on October 30; that site is operating sporadically, when sufficient radiation is available to its solar cell. Bill will travel to Valley Creek next week to address these issues. 10/17/2003 09:37 Carter_S -------- Original Message -------- Subject: Re:VC-2 still Date: Mon, 13 Oct 2003 15:33:01 -0600 From: Gary & Laurii Gadwa Reply-To: Gary & Laurii Gadwa To: pittag@psmfc.org, Steve.Achord@noaa.gov, Bill.Wassard@noaa.gov References: <200310132015.h9DKFCQE011574@blueback.psmfc.org> Hello Bill, Generator battery too low to turn over the Generator!!!! Voltage 24.8 via sun.....But when I went to Restart the laptop as it is down. It came up with needing password in order to Startup......Whats with that????????? Laptop is still OFF. I have no idea what you are using for password if you are.......What did you do to fix that issue last time????? I have charged up the Generator battery that was sitting on the floor of the Trailer. Will install it but I think you need to have whoever does it.....Have the Propane Tanks filled. I think maybe one tank has a little Propane and thats all. We'll see if Generator will start......But sure is plenty of Solar Charging conditions with the cloudless sky. GARY I am a nobody, and nobody is perfect; therefore I am perfect.......NOT ----- Original Message ----- From: To: ; ; Sent: Monday, October 13, 2003 2:15 PM Subject: Problems with remote data sites... > The following problems with remote sites were detected; > > vc2: Last data submission was received on Sat Oct 11 6:04:17 PST 2003 > > Please check this out. > > 09/29/2003 16:20 Dave Bill Wassard let us know that they're experiencing technical difficulties with VC2, which may not be fully resolved until the end of the work week. Data file creation and transmission may be intermittent during that time. 07/09/2003 16:45 Dave Interrogation activities resumed at VC2 at 1600h on 7/8/03. 06/02/2003 13:42 Dave Bill Wassard notified us that both Valley Creek interrogation installations were flooded out sometime on Saturday, May 31. The sites have been deactivated pending repairs and maintenance. Per Bill's request, I turned site checking off for VC1; site checking for VC2 has been off since last November. The last file received from VC1 was VC103150.B (ending at 12:00 on 5/30); the last file from VC2 was VC203150.C (ending at 18:00 on 5/30). 05/18/2003 18:35 Dave I surmise, from the time stamps when the VC1 and VC2 data files are uploaded, that these sites are reporting on Mountain Daylight Time (MDT). 05/06/2003 11:01 Dave Per Steve Achord, the antenna at VC2 was re-installed on May 1. It looks like data collection began at ~9:45 am. 04/11/2003 11:22 scott Per Bill Wassard, the instream antenna washed out of the stream bed this morning shutting down Pittag detection. The interrogation platform will continue to submit data files to PTAGIS. NMFS will be back on site 4/29/03 to re-install antenna. 01/01/2003 12:20 Dave Initialized new event log for 2003. 2002 event log has been archived. ####End of Event Log for VC2###